* The work in progress looking across the area towards Corwen.
In the course of a four-day exercise
beginning on April 15, a team of Llangollen Railway's Corwen Project volunteers helped local contractor
Arwel Dolben with infilling the gap in the railway embankment.
This
has long been seen as the major obstruction in completing the railway line
through to the new Corwen terminus.
Many tonnes of infill material have
been recovered from the old Ruthin branch embankment and brought round by the
dumper loads to the site of the gap.
The infill has required careful
layering and rolling to provide a firm base as the level was brought up by 10
feet in places across the width of the former trackbed.
At the end on the first phase of the
exercise project manager Richard Dixon-Gough said:
" May I, on behalf of the project team and Llangollen
Railway, express my thanks and gratitude to all who have worked so hard over
some long days and taken on the physical effort to achieve so much this week.
"With the
support of our contractors we have literally moved mountains and the first
phase of the exercise has been virtually completed. Without the input from
everyone involved this would not have happened."
The cost of the exercise was
met through the Infill the Gap appeal for donations which has raised over
£10,000 from supporters and well wishers, with £500 coming from a charity
raffle organised by Corwen townsfolk.
Completion of the final phase
of the project will continue after Easter. When complete new track will be laid
to connect the existing railhead with the loop line in the platform area.
No comments:
Post a Comment