Work planned for week starting April 11 on the Llangollen 2020 project is:
- Begin paving Yorkstone around Town Hall
- Remove lamp columns on the west side of the bridge.
- Three-way traffic management to remain on the bridge but removed by Thursday evening for the Easter Bank Holiday weekend.
- Complete drainage works on n
orth side of Abbey Road and Mill Street.