Work planned for the coming week on the 2020 project being carried out in the town centre by Denbighshire County Council's contractors includes:
Monday 11 October 2021
Bridge Street in front of Royal Hotel: finish excavating existing paving and preparing ground to the correct levels.
Castle Street (Parade Street to Market Street): finish excavating for new kerb position.
Tuesday 12 October 2021
Bridge Street in front of Royal Hotel: digging out for new drainage and installing new drainage.
Castle Street (Parade Street to Market Street): digging out for new drainage and installing new drainage.
Wednesday 13 October 2021
Bridge Street in front of Royal Hotel: continuing work for the new drainage and installing the new drainage.
Castle Street (Parade Street to Market Street): continuing work for the new drainage and installing the new drainage.
Thursday 14 October 2021
Bridge Street in front of Royal Hotel: installing new kerb line.
Castle Street (Parade Street to Market Street): installing new kerb line.
Friday 15 October 2021
Bridge Street in front of Royal Hotel: installing new kerb line.
Castle Street (Parade Street to Market Street): installing new kerb line.
* For further information go to: https://www.denbighshire.gov.uk/en/parking-roads-and-travel/roadworks/llangollen-2020.aspx