Work planned on the 2020 project for the week starting tomorrow (Monday) is:
* Bridge Street (south footpath) - Install new kerb line and finish new paving formation.
* Castle Street (East footpath) - Excavate and install new kerb line and follow on with excavation for new paving formation.
* Castle Street (West footpath) - Excavate for new footpath formation in front of the library.
* Market Street (North footpath) - Excavate for new kerb line and paving formation.
And local roadworks notified by one.network is:
25 October — 28 October Delays unlikely - Some
carriageway incursion Works description:
LAY NEW GAS 1M PUBLIC... Works location:
OUTSIDE NUMBER 9 Public facing description:
Wales & West Utilities Ltd has not assigned a specific description to
this Works. Please note: Works Descriptions are not published by Wales &
West Utilities Ltd. Responsibility for works:
Wales & West Utilities Ltd Current status:
Advanced planning Works reference: XY254004000173206 |