* A site plan of the development, with Willow Street on the left and the cemetery
in the middle top.
llanblogger has been given an exclusive insight into the £25 million new homes development planned for land off Vicarage Road in Llangollen.
Earlier this year Wrexham-based family building firm SG
Estates acquired the 10-acre site from the Castlemead Group which secured
planning permission for the scheme in late 2016.
Castlemead completed a small number of houses on a section of the site but not before it had run into a storm of criticism from a well-organised campaign group whose members objected to the wider development for the extra traffic it would create and the additional burden it would place on local services, such as schools.
Castlemead completed a small number of houses on a section of the site but not before it had run into a storm of criticism from a well-organised campaign group whose members objected to the wider development for the extra traffic it would create and the additional burden it would place on local services, such as schools.
There was particular concern about the timing of the
construction of a new access road to the development, which opponents demanded
should be finished before building work on the houses began.
However, Steve Griffin, managing director of SG Estates
which bought the undeveloped section of the site from Castlemead last February,
has given a pledge that the road, which will bring traffic up from the town
centre, will be completed ahead of construction of the homes.
Mr Griffin said what his company now planned was the main
body of the development and would include 95 units.
The extensive site stretches from Vicarage Road in the north
towards Fron Bache in the south and from the cemetery and allotments and fields
in front of them in the west to open fields in the east.
Nine of the properties will be affordable homes, in either
two-bedroom mews style or semis, the occupation of which will be overseen by a
housing association yet to be decided.
* The development site as it looks at the moment.
|
Sixty per cent of the rest of the homes will be either two or three bedrooms with the remainder four or five bedroom units.
Prices of the properties will range from £150,000 to half a
million pounds.
Mr Griffin said that overall his company is pumping £25
million into the development – it’s yet to be given a d name – which includes a
contribution of £47,000 towards the affordable homes and, as agreed within the
original planning permission, a contribution of £173,000 to local education
which schools can spend as they see fit.
Eighty-five per cent of the properties in the development
will qualify for the Welsh Government’s Help to Buy scheme, which means they
can be secured with a deposit of just five per cent.
This, explained Mr Griffin, would mean that, for example, a £200,000
property could be obtained with a deposit of £10,000.
He said: “I believe this will be particularly attractive to
first-time buyers and young families.”
The landscaped site will feature four public open spaces
with children’s play equipment and the main frontage is to be planted with oak
trees.
First job, according to Mr Griffin, is to start work on the
new access road within the next eight to 10 weeks.
The road will begin by branching off from Hall Street and
lead into Willow Street which will be widened to 9.5 metres from its present
3.5 metres.
SG Estates has purchased parcels of land along the left hand
side of Willow Street heading up from the town from both private owners and the
local authority to enable the widening operation to take place and no
properties are affected.
The new road heads on past the youth centre where the
company will upgrade the car park and put in four extra parking spaces.
The road then branches off left on a new section across the adjacent
field. It follows the line of Vicarage Road into the housing development before
joining up with the existing new section of road outside the homes built by Castlemead.
The original and narrower Vicarage Road will become a cycle
path and pedestrian walkway.
Mr Griffin revealed that the new road and the diversion of
services into the development site is costing £1.4 million.
He assured that construction work on the new homes would only
start after the access road is finished which he estimates will take about 12
weeks.
He is therefore aiming for building work to start around
next February with the first batch of new homes being ready for occupation in the
late summer of 2019. The entire development will take just over four years, he
added.
Before the road project starts he has promised full
consultation with affected residents and their local council representatives.
Mr Griffin, whose background is in building, said: “This is
a very exciting time for the company, which we started in 2004.
“We have ongoing developments in Pont Adam, Ruabon and The
Pavilions, Gresford, but this will become our biggest site and the overall cost
of £25 million represents a very big investment for us.
“Our watchword is quality and we regularly win quality awards
from local authorities.
“The Llangollen development will be beautiful when it is
finished and I believe it will add vibrancy and bring a fresh outlook to the
town, which I love to visit.
“Possibly, when we move onto the site and take a closer look
at density the number of units in the development could be reduced at the
southern end towards Fron Bache.”