Tuesday, September 21, 2021

Resurfacing work on A483 planned for October

Essential resurfacing work is to take place on the A483 in Wrexham between Junction 6 Gresford and Junction 7 Rossett between October 11 and 14.

The main works will be carried out under contraflow which will allow the A483 to remain open to one lane of traffic in either direction. 

This will enable the works to be carried out on the closed carriageway efficiently and safely. 

There will be full overnight closures at certain times within the programme, to enable the installation and dismantling of the traffic management system.

Traffic Wales says the project will address the deteriorating condition of the carriageway to eliminate the current ongoing and increasing requirement for reactive repairs. 

This will ultimately mean less disruption for motorists in future and will deliver a safe, quiet, high-quality road surface for many years to come.

A483 Northbound works between between junction 7 Rossett to junction 6 Gresford

Overnight full carriageway closure from October 11th-14th for 3 nights, October 23rd to 25th for 2 nights and October 28th for 1 night.

Daytime lane closures from October 11-13th for 2 days

Contraflow (all traffic on southbound carriageway) from October 14th-28th. Apart from overnight on October 23rd and 24th.

Overnight closure on Junction 6 Gresford northbound onslip and offlsip from October 11th-14h for 3 nights. 24h closure on on Junction 6 Gresford northbound onslip and offlsip from October 13th-28th

A483 Southbound works between junction 6 Gresford to Junction 7 Rossett

Overnight full carriageway closure from October 29th-30th for 1 night, November 11th-13th for 2 nights.

Daytime lane closures on October 29nd and November 12th

Contraflow (all traffic on northbound carriageway) from October 30th to November 11th.

24h closure on Junction 6 Gresford southbound onslip and offlsip from October 29th to overnight on November 13th. No closure during the daytime on November 12th

* For further information, please contact Traffic Wales on 0300 123 1213 or via Twitter @TrafficWalesN