* The Wharf steps where limited progress has been made.
The completion date for Llangollen’s Four Great Highways
scheme has now been moved back by another month, which means it is now three
months behind schedule.
Earlier this week llanblogger reported that there had been
little progress made on certain aspects of the project, which was funded by the former Conservative
government’s Levelling Up Fund and aims to “enhance the landscape and
improve accessibility, interpretation and signage in the centre of
Llangollen”.
And we pointed out that there was less than a fortnight to
go before the completion deadline of the end of August was reached – which itself
had been moved back from June.
Today the project team revealed there’s been
another change of plan and the scheme will not now be completed until the end
of September.
In an update they say: “As you may be aware the last update we provided
advised that the project would be completed by the end of August 2024.
“Unfortunately, despite the contractor working weekends to try and
mitigate the time lost we are still running slightly behind due to a few issues
in both areas - ground condition challenges at the Wharf and a slight re-design
to the steps structure in Lower Dee Mill Park to accommodate the steel
structure ramp.
“In addition to this there is final landscaping works, which will be
carried out in September 2024 as the correct time of year for certain planting.
“Due to this delay, the planned completion date for the project is now
end September 2024, however please be assured the contractor is working
very hard to complete some aspects of the scheme sooner if and where
possible. The signage and wayfinding aspect of the project will also be
installed before the end of September 2024.
“We sincerely apologise for any inconvenience and disruption this may
cause and appreciate your patience while the contractor works hard to complete
this project for us.”
The first delay occurred when the scheme
ran into unexpected ground conditions with its two key aspects - a raised
walkway at Lower Dee Mill Park and the improvement of the flight of steps up
from Abbey Road to the canal wharf.
An update from the team in early August
said that because of a delay while steel supports were delivered the scheme
would be finished by the end of this month.
But earlier this week while work at
Lower Dee Mill Park appeared to be catching up well there seemed to have been
little progress on the Wharf steps.
On Monday morning workmen were busy
putting what looked to be the finishing touches to the park walkway but while
large steels supports had been installed
at the top end and a mechanical digger was on site, there were few signs of any
start being made on the wharf steps.
The project is part of a Levelling Up
investment secured through a joint application between Denbighshire County
Council and Wrexham County Borough Council for the old Clwyd South Constituency
– Llangollen is now part of the new Clwyd East.
The application was supported by former
MP for the area Simon Baynes and £3.8 million was allocated to Denbighshire to
invest in the communities of Llangollen, Llantysilio, Corwen and surrounding
areas.