Wednesday, April 5, 2023

Weeks of roadworks planned for A525 Nant y Garth Pass

Roadworks are due to commence on the A525 at Nant y Garth later this month.

These comprise carriageway patching,  road cleansing, gully emptying and the reconstruction of a damaged section of wall supporting the carriageway.

The works will take place from B5429 Llysfasi to B5431 to Llanarmon Yn Ial.

Work is due to start on Monday April 17 and is expected to take up to six weeks to complete.

Initially, the road will be closed for vehicular traffic and pedestrians from Monday April 17 to Wednesday  April 19 and thereafter, two-way temporary traffic signals will be in place for a further five weeks to undertake the retaining wall works. Public Transport will operate as normal.

Access to residential and business premises which are located on Nant y Garth will be available although some delay and disruption maybe experienced and residents are encouraged to keep journeys to a minimum to reduce traffic congestion.

The alternative diversion route will be signed accordingly. Normal working hours shall apply to the works.

Cllr Barry Mellor, Lead Member for Environment and Transport, said: “Denbighshire County Council apologise for any inconvenience that these essential works may cause, and we are grateful for local cooperation and patience during this time to ensure that the works are completed as quickly and efficiently as possible.”

No comments:

Post a Comment