Sunday, October 24, 2021

2020 project - work planned for this week

Work planned on the 2020 project for the week starting tomorrow (Monday) is:

* Bridge Street (south footpath) - Install new kerb line and finish new paving formation.

* Castle Street (East footpath) - Excavate and install new kerb line and follow on with excavation for new paving formation.

* Castle Street (West footpath) - Excavate for new footpath formation in front of the library.

* Market Street (North footpath) - Excavate for new kerb line and paving formation.

And local roadworks notified by one.network is:

 

Chapel Street


25 October — 28 October

 

Delays unlikely - Some carriageway incursion

 

Works description: LAY NEW GAS 1M PUBLIC...

 

Works location: OUTSIDE NUMBER 9

 

Public facing description: Wales & West Utilities Ltd has not assigned a specific description to this Works. Please note: Works Descriptions are not published by Wales & West Utilities Ltd.

 

Responsibility for works: Wales & West Utilities Ltd

 

Current status: Advanced planning

 

Works reference: XY254004000173206 